Karnataka State Highways Improvement Project-II Package Details

World Bank funded Packages (World Bank Loan No.8022-IN)

As on March 2024
Package  No Description of Road  Name of Contractor Length in kms Contractor Period (in months) Contract Amount (Rs.in Cr.) Expenditure INR in Crores (Upto March 202) Starting Date as per Contract Completion Date as per Contract Actual Date of Completion Status
KSHIP-II World Bank - EPC contracts 
WEP-1 Upgradation of road from Hoskote to Chintamani Bypass  M/s Lanco Infratech Ltd., 52.44 30 98.22 116.67 13-08-2011 12-02-2014 30-05-2015  Completed
WEP-2A Upgradation of road from Haveri to Hangal M/s DRN Infrastructure 31.78 21 92.53 95.9 02-03-2013 01-12-2014 27-06-2016 Completed
WEP-2B Upgradation of road from  Hangal to Tadasa  M/s DRN Infrastructure 43.46 21 97.87 93.09 20-07-2013 19-04-2015 31-01-2017 Completed
WEP-3 Upgradation of road from Dharwad to Saundatti  M/s RVCPL-RIDL JV 36.00 23 80.00 87.04 28-07-2011 28-06-2013 31-01-2016 Completed
WEP-4 Upgradation of road from Tinthini to Kalmala  M/s Patel Engineering Ltd 73.76 36 160.69 197.78 13-08-2011 12-08-2014 24-06-2015 Completed
WEP-5 Upgradation of road from Chowdapur to Gulbarga  M/s SRK-KCL JV 28.63 18 61.55 65.10 19-07-2011 18-01-2013 25-04-2014 Completed
WEP-3A Upgradation of Road length of  2.50 Kms of Dharwad to Saundatti in Dharwad town limits M/s The Trinity Group, Hubli 2.50 15 18.40 16.78 01-12-2017 28-02-2019 07-10-2021 Completed
      268.57   609.26 672.36        
KSHIP-II World Bank - Annuity Converted EPC Contracts 
WAEP3A Upgradation of road from Shimoga- Shikaripura-Anandapura M/s Patel Engineering Ltd. 82.04 32 264.73 278.62 12-08-2015 11-04-2018 30-11-2018 Completed
WAEP3B Upgradation of road from Shikaripura to Hangal M/s RNS Infrastructure Ltd 71.63 29 224.70 268.58 01-10-2015 28-02-2018 12-05-2019 Completed 
WAEP4 Upgradation of road from  Managuli to Devapura M/s. Sadbhav Engineering Limited, Ahmedabad 102.49 33 317.05 324.42 27-07-2015 26-04-2018 20-07-2018 Completed (excluding descoped length of 7.453 kms due to LAQ issues)
      256.16   806.48 871.62        
KSHIP-II- World Bank  Hybird Annuity Packages
WAP 1
  
Malavalli to Pavagada  M/s Mysore Bellary Highway Pvt Ltd
(M/s Sadbhav-GKC (JV))
193.34 30 months + 90 months maintenance Rs.1306 Cr
(239 cr  + 15 installments of    Rs. 71.15 cr)
1201.95 12-12-2014 12-06-2017 20-09-2018  Completed and is under O & M period
WAP 2 Mudhol to Nippani  M/s Ashok Buildcon-GVR (JV) 107.94 24 months + 96 months maintenance  Rs.768 Cr
(136 cr  + 16 installments of  Rs. 39.49 cr)
698.71 12-12-2014 12-12-2016 12-12-2017  Completed and is under O & M period
      301.28   2074 1900.66        
KSHIP-II- World Bank -KRDCL-Cofinancing Contracts 
WCP-1 Upgradation of Road from Bagewadi (NH-4)- Bailhongal - Saundatti  M/s Ashoka Bagewadi Soundatti Road Ltd. 63.29 24 months + 96 months maintenance Rs.622.704 Cr
(75.504 cr  + 16 installments of    Rs. 34.20 cr)
421.37 03-10-2016 02-10-2018 01-10-2018  Completion certificate issued on 31-08-2020
WCP-2 Upgradation of Road from Bidar Ekhelli Chincholi  D.P.J Bidar Chincholi (Annuity) Road Project Private Limited 60.04 24 months + 96 months maintenance Rs.472.224 Cr
(72.384 cr  + 16 installments of    Rs. 24.99 cr)
272.88 04-08-2017 03-08-2019 03-08-2019 PCOD declared on 03.08.2019. 
WCP-3 Upgradation of Road from Hassan - Ramanathapura - Periyapatna  M/s DBL Hassan Piriyapatna Tollways Ltd. 73.69 24 months + 96 months maintenance Rs.509.252 Cr
(88.772 cr  + 16 installments of    Rs. 26.28 cr)
368.39 29-09-2016 28-09-2017 28-02-2018 PCOD declared on 03.08.2019. 
WCP-5 Upgradation of Road from Hirekerur to Ranibennur  M/s DBL Hirekerur Ranibennur Tollways Ltd. 55.69 24 months + 96 months maintenance Rs.384.296 Cr
(70.376 cr  + 16 installments of    Rs. 19.62 cr)
266.65 29-09-2016 28-09-2017 24-02-2018 . PCOD declared on 03.08.2019. 
WCP-6 Upgradation of Road from Mundaragi - Hadagali - Harapanahalli M/s DBL Mundaragi Harapanahalli Tollways Ltd. 51.21 24 months + 96 months maintenance Rs.348.332 Cr
(64.652cr  + 16 installments of    Rs. 17.73 cr)
248.81 29-09-2016 28-09-2017 05-02-2018 PCOD declared on 03.08.2019. 
WCP-7 Upgradation of Road from Hungund - Muddebihal -Talikot M/s Ashoka Hungund Talikota Road Ltd. 56.98 24 months + 96 months maintenance  Rs.568.129 Cr
(65.569 cr  + 16 installments of  Rs. 31.41 cr)
373.15 03-10-2016 02-10-2018 01-10-2018  Completion certificate issued on 31-08-2020
      360.90   2904.94 1951.25        
TOTAL  1,186.91   6394.68 5397.98        

 Note: Out of Original 1195  Kms ,around 9 kms  descoped.

 

Asian Development Bank-funded Packages (ADB Loan No.2705-IND)

As on March 2024
Sl. No. Package no Description of Road Contractor Name (M/s) Length in  kms Contract Period
(in months)
Contract Amount (Rs.in Cr.) Cumulative Expenditure (Rs.in Cr.)
 (As on March 2024)
Starting Date as per Contract Completion Date as per Contract Actual Date of Completion Status
1 AEP-1 Upgradation of the Road from Magadi NH-48 (Km.0+000) to Koratagere (Km 68+200) of SH-3 (Length - 68.2 km) KNR Construction Ltd., Hyderabad 68.20 33 116.78 129.69 21-03-2012 20-12-2014 31-12-2016 Completed
2 AEP-2 Upgradation of the Road from Pavagada (Km.0+000) to AP Border (Km 23+210) of SH-3 (Length - 23.21 km) GVR-RMN JV 23.21 18 43.30 46.63 29-03-2012 28-09-2013 28-06-2014 Completed
3 AEP-4 Upgradation of the Road from Jaglur to NH-13 of SH-45 (Approx length=9.25 Kms) & Upgradation of the Road  of about 5 Kms from SH-19 of KSHIP Road to Molakalmuru  of SH-2 (Length - 14.38km) GVR-RMN JV 14.38 15 31.25 33.41 21-03-2012 20-06-2013 15-03-2015 Completed
4 AEP-5 Upgradation of the Road from Padubidri (Km.0+000) to Karkala (Km 27+800) of SH-1 (Length - 27.80 km) RNS Infrastructure Limited 27.76 18 61.47 80.05 21-03-2012 20-09-2013 22-05-2015 Completed
5 AEP-7 Upgradation of the Road from Shelvadi (Km.0+000) to Mundargi  (Km 63+440) of SH-45 (Length - 63.44 km) KNR Construction Ltd., Hyderabad 62.68 33 121.54 146.93 21-03-2012 20-12-2014 19-03-2016 Completed
6 AEP-8 Upgradation of the Road from Mudgal (Km 0+000) to Gangawathi (Km 74+200) of SH-29 (Length - 74.20 km) KNR Construction Ltd., Hyderabad 74.20 36 152.62 180.40 26-03-2012 25-03-2015 25-02-2015 Completed
    SubTotal 270.43   526.96 617.11        
7 AEP-3A Upgradation of Road from Gubbi to Beeragonahalli near Yediyur (49+030 kms) of SH-84 DRN Infrastructure 49.03 21 122.38 178.78 14-12-2015 13-09-2017
04-04-2018
Completed
8 AEP-3B Upgradation of Road from Beeragonahalli near Yediyur (0+00 kms) to Mandya ( 59+590 Kms) of SH-84 DP Jain & Co. Infrastructure Pvt.Ltd. 58.38 21 198.27 235.48 09-09-2015 08-06-2017
22-10-2018
 Completed . 1.21 km dropped from Scope of Contract"
9 AEP-6A Upgradation of Road from Davanagere (0+00 kms) to Channagiri ( 53+650 Kms) of SH-76  JMC Projects (India) Ltd. 51.29 21 181.45 206.04 15-12-2015 14-09-2017
31-10-2018
Completed
10 AEP-6B Upgradation of Road from Channagiri (0+00 kms) to Birur  (51+980 Kms) of SH-76  DP Jain & Co. Infrastructure Pvt.Ltd. 50.58 21 136.79 174.65 05-11-2015 05-08-2017
22-10-2018
Completed
11 AEP-9A Upgradation of Road from Saundatti (0+00 kms) to Ramdurga ( 38+465 Kms) and Ramdurga to Halgatti Junction, Ramdurga (0+00 to 3+600 Kms) DP Jain & Co. Infrastructure Pvt.Ltd. 42.07 21 138.25 181.15 24-09-2015 23-06-2017
31-05-2018
Completed
12 AEP-9B Upgradation of Road from Halgatti Junction, Ramdurga (Km 3+600) to Badami (Km 45+730) and from Badami to Badami Bypass Junction (Km 0+00 to Km 2+870) RNS Infrastructure Ltd., 43.58 21 146.05 142.59 04-09-2015 03-06-2017
05-10-2018
Completed
13 AEP-9C Upgradation of Road from Badami Bypass junction (Km 2+870) to Pattadakallu (Km 21+530) and Pattadakallu (Km 0+000) to Kamatagi (Km 22+280) including Badami Bypass (2.190 Km) Ashoka Buildcon Limited 43.13 21 110.90 115.06 24-09-2015 23-06-2017
31-10-2018
Completed
SubTotal   338.06   1034.09 1233.75        
14 ROB1 Ch. 7.691 Railway km 316/200-300. Tholahonse village on Davanagere-Channagiri Road AEP6A KNR Construction Ltd., Hyderabad 1.38   39.79 51.72 27-11-2014 26-11-2016 30-12-2019 Completed
15 ROB2 Ch. 44.830 Railway km 219/900-220/000. near Birur on Birur-Channagiri Road AEP6B K.VenkataRaju, Vijayawada 1.4   36.10 40.00 07-03-2015 06-03-2017 22-10-2018 Completed
16 ROB3 Ch.25.339 Railway km 55/200-300. on Gadag Bypass on Shelvadi-Gadag route AEP7 KNR Construction Ltd., Hyderabad 1.55   22.66 24.23 25-04-2014 24-04-2016 31-10-2016 Completed
17 ROB4 Ch.42.214 Railway km 60/600-700. near Badami on Ramdurga-Badami route AEP9 KNR Construction Ltd., Hyderabad 1.42   28.58 30.24 12-11-2014 11-11-2016 30-04-2017 Completed
    SubTotal 5.75   127.13 146.19        
    Total   614.24   1688.18 1997.06        

 

Karnataka State Highway Improvement Project – II (KSHIP-II)

Government of Karnataka taken up KSHIP- II to further improve state highways. Strategic Option Studies were carried out on l4,090 Km of State Highways. Feasibility studies were conducted on selected 4888 km roads. The selection of roads for preparation of Detail project report was based on ranking with 80 % weightage for economic internal rate of return and 20% weightage for Deprivation Index derived from Dr Nanjundappa committee report for redressal of regional imbalances. Finally, 3411 Km of State Highways are identified for improvement, which is approved by the Cabinet in Nov 2006. A Government Order was issued to notify the consultants to prepare DPR for selected 3411 kms vide No. PWD 61 EAP 2006 dated 25.11.2006. Consultants M/s.Scott Wilson Ltd., U.K in Jv with Scottwilson India Ltd,Delhi prepared the DPR for 3411 Kms.

After successful completion of KSHIP-1 and as per the Government order no PWD 61 EAP 2006 dated 25-11-2006 the improvement of 3411kms of State Highways of the Core Road Network of the State was initiated under KSHIP-II. All the roads under KSHIP-2 were planned for upgrading to a min. 2 Lane carriageway with geometric improvements.  The list of roads prioritized for improvement under KSHIP-II is provided below: 

GO No. PWD 61 EAP 2006 Bangalore Dated: 25-11-2006

List of Selected Roads For Improvement Under KSHIP-II

Name of the Roads

km

Tinthni-Devadurga-Kalmala

74

Kushtagi (NH-13)-Tawargera-Sindhanur

64

Managoli-Talikota-Devapur

110

Mudgal-Kudithini (NH-63)

115

Konannanur-Hunsur-HD Kote

89

Sira-AP Border via Madhugiri-Gowribidanur-Chikaballapura-Chintamani-Srinivasapura-Mulbagal

210

Haliyal-Kudalasangama via Dharwad-Soundatti-Ramdurga-Badami-Pattadakal-Kamatgi-NH13

243

Hassan-Periyapatna via Arakalagud-Ramanathpura

77

Hirekerur-Ranebennur (on NH-4)

58

Kudachi-Kabbur-Ghataprabha

50

Shikaripura-Anandapuram (on NH-206)

32

Kotumachigi-Gajendragarh

32

Goa Border-Soundatti via Khnapur-Bagewadi-Bailhongal

133

Mudhol-Nippani via Mahalingapur-kabbur

104

Belur-Kodlipet via Bikkodu-vatehole-Alur-Magge

72

Davenagere-Birur via Channagiri

104

Gangamula-Kottigehara

63

Hangal-Haveri (NH-4)

32

TN Border (Hunasanahalli)-AP Border via Kanakapura-Ramanagara-Magadi-Dobbespet-Koratagee-Madhugiri-Pavagada

220

Hole Narsipura to K.R.Nagar via Saligaram

46

Shelavadi-Harapanahalli via Gadag-Mundarigi

112

Indi-Zalaki (on NH-13)

20

Maharastra Border – Gulbarga via Afzalpur

99

Hungund-Talikot via Muddebihal

58

Gubbi-Mandya via Yediyur-Kowdle

109

Jagalur-NH-13

10

Hoskote-AP Border via Chintamani

88

Belthangadi to Bantwal (on NH-48)

35

Ramangaram-Saligramma via Thalavadi-Choulnankuppe-Huliyurdurga-Nagamangala-K.R.Pet Akkihebbal -Berya

142

Malavalli-Koratagere via Maddur-Kunigal-Tumkur

135

Shimga-Tadasa on NH-4 via Savalanga via Shikaripura-Shiralakoppa-Togarsi Anvatti-Gondi-Hangal

171

Jamkhandi-Maharastra Border via Terdal-Kudachi-Managsuli

79

Horanadu-Subramananya via Kalasa-Kottigehara-Mudigere-Sakaleshpura Junction- Vanagur

164

Molkalmur to SH 19 (KSHIP1 Road)

6

Bidar-Chincholi via Ekhelli (NH9)

61

Padubidri-Karkala

28

Kollegala-Tamilnadu Border via Hanur-MM Hills

97

Virajpet-Somawarpet via Madikere

71

Total Length (Kms)

3,411

KSHIP-II was taken up in two stages. The Stage-1 was taken up in 2011 with the World Bank finance and Stage-2 in 2012 with the ADB finance.

KSHIP-II – STAGE – I – World Bank Project:

Initially the World Bank sanctioned a loan assistance of US$ 300 million with an overall project size of Rs.2545 crore. Following the Loan Negotiations held with the World Bank and DEA, GOI in February 2011 the Project cost underwent a significant revision. With the concurrence of the DEA, GOI the Loan was enhanced from US$ 300 million to US$ 350 million and further the World Bank also enhanced the component size under the “Highway financing Modernisation” from Rs. 50 crore (US$ 10 million) to Rs. 1682 crore   (US$ 374 million) which was aimed at assisting KRDCL in implementing the concept of Co-financing (Private financial institutions) to develop about 361 km of highways under either Item-rate contracts or PPP concessions. The Project Cost was revised from the initial Rs. 2545 crore (US$ 565 million) to Rs 4522 crore (US$ 1005 million).

The details of the Loan agreement with the World Bank are:

  1. Loan no: 8022-IN
  2. Loan Signed date: 30-05-2011
  3. Loan Effectiveness date: 19-07-2011
  4. Project Cost: US$ 1005 million (Rs.4522 Cr)
  5. World Bank Share: US$ 350 million (Utilised US$ 295.21 million)
  6. GOK Share: US$ 155 million (Rs.697 Cr)
  7. Private Sector/ Developer/KRDCL Share: US$ 500 million (Rs.2250 Cr)
  8. Loan Closing date: 31-12-2016 (Extended upto 28th Dec, 2018)
  9. Loan Amortization Schedule: 15-06-2016 to 15-03-2029.

The implementation of World Bank assisted KSHIP-2 under Stage-1 and the list of roads of 834 kms received the approval of the Government vide GO no. PWD 13 EAP 2010 dated:28-06-2010 and GO no. PWD 121 EAP 2011 dated: 04-02-2012.

 

A total of 1195 lms road length (KSHIP 834 kms + KRDCL 361 kms) was taken up for improvement at a total project cost of Rs 4522 crores under KSHIP-2, out of which World Bank loan assistance is Rs 1575 Crores. The Project was implemented in following contracts;

EPC Contracts (269 kms):

The EPC contracts are Item Rate contracts with a defect notification period of one year and the World Bank would fund 80% of the contract cost. The contracts for the five EPC packages were procured observing ICB procedures and commenced in July/August, 2011. The contract WEP2 from Haveri- Hangal-Tadas (75 kms) entrusted to M/s Roman Tarmat, Mumbai was terminated due to non-performance in Nov, 2012 and retendered by splitting the contract into two NCB contracts WEP2A & WEP2B. The contract for WEP2A and WEP2B were signed in Feb, 2013 and June 2013 respectively. The improvement was taken up at a contract amount of Rs 596 Cr in six contracts having duration of 18 to 36 months.

Subsequently, a part of the road of Contract WEP3 Upgradation of Road from Dharwad to Saundatti for a length of 2.50 Kms in Dharwad town limits was converted from Upgradation to Tender Sure model as a separate package (WEP-3A) in Oct 2017.

 The details of the contracts are as under:

Contract No.

Contract Name

Length (km)

Contractor

Contract Price in Rs. Crore

Present status

WEP-1

Upgradation of the Road from Hoskote to Chintamani

52.40

M/s Lanco Infratech Ltd, Gurgoan

98.22

Completed

30-05-2015

WEP2A

Upgradation of the Road from Haveri (NH-4)   to Hanagal

31.78

M/s DRN Infrastructure, Hubli

92.53

Completed

27-06-2016

WEP2B

Upgradation of the Road from Hanagal to Tadas

43.50

M/s DRN Infrastructure, Hubli

97.87

Completed

31-01-2017

WEP-3

Upgradation of the Road from Dharwad  to Saundatti

36.00

M/s RVCPL- RIDL (JV), Bangalore.

84.44

Completed

31-01-2016

WEP-4

Upgradation of the Road from Tinthini  to Kalmala

73.80

M/s Patel Engineering Ltd, Hyderabad.

160.68

 

Completed

24-06-2015

WEP-5

Upgradation of the Road from Chowdapur to Gulbarga

28.63

M/s SRK-KCL (JV), Hyderabad.

61.55

 

Completed

25-04-2014

WEP-3A

Upgradation of Road length of  2.50 Kms of Dharwad to Saundatti in Dharwad town limits Tender sure

2.50

M/s The Trinity Group, Hubli

18.40

Completed

 

 

268.57

 

609.26

 

The total cost incurred for theses contracts is around Rs 672.35 crore as on March 2024.

Annuity contracts (301 kms):

The Annuity Contracts are of 10 years duration with max. of 2 to 21/2 years of construction and 8 to 71/2 years of maintenance. Under Annuity Contracts, the World Bank assistance is utilised for an upfront payment of 50% of the construction cost on completion of the construction and the remaining payments of 50% to be funded by GOK during the maintenance period of 71/2 years on annuity basis. The details of the roads taken up under Annuity mode are as below:

Package Name of the road Length kms Concessionaire Construction Cost(Rs in Cr) Contract Cost(Rs in Cr) Present status
WAP-1 Malavalli – Maddur – Huliyurdurga- Kunigal- Tumkur- Koratagere- Madhugiri- Pavagada 193.36 M/s Mysore Bellary Pvt Ltd (M/s Sadbhav-GKC (JV)) 576 1306* Completed on 20-09-2018 And Under O & M period
WAP-2 Mudhol – Mahalingapura- Kabbur- Chikodi-(NH-4 cross) Nippani. 107.94 M/s Ashok Buildcon-GVR (JV) 331 768** Completed on 12-12-2017 And Under O & M period
    301.30   907 2074  

* 239 cr lumpsum during construction + 15 Annuity installments of Rs. 71.15 cr

** 136 cr lumpsum during construction + 16 Annuity installments of Rs. 39.49 cr

The Agreements were signed in 24-03-2014 for WAP1 and 14-03-2014 for WAP2. The works were commenced on 12-12-2014 after achieving financial closure and fulfilling the conditions precedent.

The Project work of WAP1 was completed on 20-09-2018 and the Project work of WAP2 was completed on 12-12-2017. The road works are presently in Operation and Maintenance period. The O & M period will be upto 2024-25.

Annuity contracts converted to Item rate Contracts: (264 kms):

The Two contracts of WAP3 and WAP4 with a total length of 264 kms had been initially proposed to be taken up under Annuity model. As the annuity bids did not yield value for money, the bids were cancelled. The contracts were re-procured and implemented under three Item Rate contracts.

The brief details of the contract works are as under:

Package Name of the road Length kms Contractor Contract Cost (Rs in Cr) Contract duration in months Contract agreement date Commencement / completion dates
WAEP 3A Shimoga -Shikaripura - Anandapuram 82.00 M/s Patel Engineering Ltd 264.73 32 28-04-2015 12/08/2015
30/11/2018
WAEP 3B Shikaripura – Anvatti- Hangal 71.63 M/s RNS Infrastructure Ltd 224.70 29 06-07-2015 01/10/2015
12/05/2019
WAEP 4 Managuli to Devapura 109.95 M/s. Sadbhav Engineering Limited 317.05 33 30-04-2015 27/07/2015
20/07/2018
    263.58   806.48      

A road length of 256 kms has been completed at cost of Rs.871.62 crore upto end of March 2024. The road work for WAEP4 has been completed deleting a reach of 7.453 kms from the scope which was affected by LAQ.

KRDCL- (Co financing PPP Contracts) (361 kms):

A road length of 361kms from out of 3411 kms is taken up for improvement through PPP contracts under Co-financing through KRDCL under Highway modernisation component of the Project. The construction cost will be shared between WB, KRDCL & Developer in the ratio of 20:20:60. The list of roads is given below:

Contract Package

 

Name of package

Length in km

Estimated Constn. cost
Rs crore

WCP-1

Bagewadi (NH-4)- Bailhongal - Saundatti

63.29

189

WCP-2

Bidar - NH-9 (Ekhelli)- Chincholi

60.04

181

WCP-3

Hassan-Ramanatpura-Periyapatna

73.69

222

WCP-5

Hirekerur - Ranibennur

55.69

176

WCP-6

Mundaragi - Hadagali - Harapanahalli

51.21

164

WCP-7

Hungund - Muddebihal -Talikot

56.98

164

 

360.90

1096

KRDCL is designated as the Implementing Agency for this project component. The original DPR was revised for the selected roads to suit the funding agency terms. Based on the Value for Money (VfM) analysis, the roads are taken up for improvement under Hybrid Annuity model. The road works are presently in Operation and Maintenance period.

 

 

Karnataka State Highway Improvement Project – II (KSHIP II) - Asian Development Bank (ADB) loan Assistance.

The brief details of the loan are as under:

  1. Loan no: 2705-IND
  2. Loan Signed date: 20-07-2011
  3. Loan Effectiveness date: 12-09-2011
  4. Project Cost: US$ 462.75 million (Rs.2150 Cr)
  5. ADB Share: US$ 315 million (Revised:US$265 million, utilized :US$ 263.2 million)
  6. GOK Share: US$ 147.75 million (Rs.687 Cr)
  7. Loan Closing date: 30-06-2015. (Rev1 date 31-12-2016,Rev2 date 30-06-2018, Rev3-31.10.2018)

A total of of road length and 4 ROBs in the project roads at a total project cost of        Rs 2150 crores was taken up with Asian Development Bank (ADB) loan assistance of US$ 315 million. With cancellation of surplus loan, the assistance is revised to US$265 million. The improvement was taken up in nine EPC packages at a total contract cost of Rs 1151cr. The contract duration varies from of 15 to 36 months. The works were commenced in March, 2012. During execution, three contracts viz AEP3, AEP6 and AEP9 were terminated. The package wise details are below:

 

 

Contract
 No.

Name of work

Approx Length (km)

Contract Period (months)

Contract amount in Rs. Crore

Status

AEP1

Road from Magadi NH-48 (Km.0+000) to Koratagere (Km 68+200) of SH-3

68.20

33

116.78

Completed

31-12-2016

AEP2

Road from Pavagada (Km.0+000) to AP Border (Km 23+210) of SH-3

23.21

18

43.30

Completed

28-06-2014

AEP3

Road from Gubbi (Km.0+000) to Mandya (Km 108+620) of SH-84

108.62

33

196.90

Terminated on 24.07.2014

AEP4

Road from Jaglur to NH-13 of SH-45 (Approx length=9.25 Kms)

Road  of about 5 Kms from SH-19 of KSHIP Road to Molakalmuru  of SH-2

14.38

15

31.25

Completed

15-03-2015

AEP5

Road from Padubidri (Km.0+000) to Karkala (Km 27+800) of  SH-1

27.80

18

61.48

Completed

22-05-2015

AEP6

Road from Davangere (Km.0+000) via Channagiri  to Birur  (Km 105+630) of SH-76

105.63

33

202.57

Terminated on 17.07.2014

AEP7

Road from Shelvadi (Km.0+000) to Mundargi  (Km 63+440) of  SH-45

63.44

33

121.25

Completed

19-03-2016

AEP8

Road from Mudgal (Km 0+000) to Gangawathi (Km 74+200) of   SH-29

74.20

36

152.63

Completed

25-02-2015

AEP 9

Road from Soundatti - Hulikatti – Ramdurg-- NH218 – Badami-Pattadakal-Kamatagi

130.13

36

225.50

Terminated on 30.10.2014

 

 

615.61

 

1151.66

 

The three terminated contracts of AEP3, AEP6 & AEP9 were re-procured splitting the roadwork into seven NCB Packages of AEP3A, AEP3B, AEP6A, AEP6B, AEP9A, AEP9B and AEP9C with lesser duration of 21 months. The details are as under:

New Package

Road

Length

in kms

Contract signed on

Contractor

Contract price

(Rs in Cr)

Status

AEP-3A

Road from Gubbi to Beerangonahalli near Yediyur of SH 84

49.03

05-11-2015

M/s DRN Infrastructure Engineers & Contractors, Hubli.

122.38

Completed 04-04-2018

AEP-3B

Road from  Beerangonahalli near Yediyur to Mandya of SH 84

59.59

18-06-2015

M/s DP Jain & Co, Nagpur

198.27

Completed 22-10-2018

AEP-6A

Road from Davangere to Channagiri of SH76

53.65

14-09-2015

M/s JMC, Bangalore

181.45

Completed 31-10-2018

AEP-6B

Road from Channagiri to Birur of SH 76

51.98

31-08-2015 

M/s D.P.Jain& co. Infrastructure Pvt. Ltd.,Nagpur

136.79

Completed 22-10-2018

AEP-9A

Road from Savadatti to Ramdurga (Halgatti Junction)

42.00

28-07-2015

M/s D.P.Jain& co. Infrastructure Pvt. Ltd.,Nagpur

138.24

Completed 31-05-2018

AEP-9B

Road from  Ramdurga (Halgatti Junction) to Badami Bypass

45.00

23-06-2015

M/s RNS Infra structure Ltd., Bangalore  

146.05

Completed 05-10-2018

AEP-9C

Road from   Badami Bypass  to  Pattadakal- Kamatagi

43.13

07-07-2015

M/s Ashoka Buildcon Ltd,Nashik

110.90

Completed 31-10-2018

   

344.38

 

 

1034.08

 

All Road works completed. The expenditure incurred towards road works is Rs. 1850.87 crore upto end of March 2024

ROB Packages:

The following 4 ROBs which are a part of the Upgradation Package AEP6, AEP7 & AEP9 have been taken up for construction under ADB loan assistance in separate contracts. The contracts have duration of 24 months. The details are as under:

Pkg

Link

Name of ROB

Contract Price

(Rs in cr)

Contractor

Agreement

Status

AEP-6 ROB-1

42A

At Chainage 7.691 , Railway Km. 316/200-300, Tholahonse Village  on Davangere Channagiri route

39.79

M/s KNR Constn Ltd, Hyderabad

17-09-2014

Completed 30-12-2019

AEP-6 ROB-2

42B

At Chainage 44.830, RLY Km 219/900-220/000 Near Birur  on Channagiri – Birur route

36.10

M/s. K. Venkata Raju Engineers & Contractors, Vijayawada.

19-09-2014

Completed

31-10-2018

AEP-7 ROB-3

27A

At chainage 25.339, RLY.KM.55/200-300 on Gadag Bypass  on Shelavadi – Gadag Route 

  1.  

M/s KNR Constn Ltd, Hyderabad

 26-12-2013

Completed

31-10-2016

AEP-9 ROB-4

21D

At Chainage 42.214, Railway Km. 60/600-700 Near Badami  on Ramdurga – Badami  route

28.58

M/s KNR Constn Ltd, Hyderabad

17-09-2014

Completed

30-04-2017

 

 

Total

127.13

 

 

 

All the four ROBs are completed. The expenditure incurred for ROB works is Rs. 146.19 crore upto end of March 2024. 

SUMMARY OF THE PROJECT WORKS of KSHIP-II:

Funding Agency

Total length (Km

Contract cost

(Rs. Cr)

Expenditure as on March 2024 

(Rs.in Cr)

KSHIP2-World Bank

 

 

 

EPC contracts (7)

268.57

609.26

672.45

Annuity contracts (2)

301.28

2,074.00

1900.66

Annuity converted to EPC contracts (3)

256.16

806.48

871.62

KRDCL Cofinancing contracts (6)

358.69

2,904.94

1951.25

Total for World Bank

1184.70

6394.68

5397.98

 

 

 

 

KSHIP2-ADB

 

 

 

EPC contracts (13)

608.49

1561.05

1850.87

ROB contracts (4)

5.75

127.13

146.19

Total for ADB

614.24

1688.18

1997.06




Land Acquisition Status of Annuity Contracts (World Bank)

Back As on 31-Oct-2014
Sl. No. Package. No. Name of the Link Link No. Total No. of Sy.No. Total Extent U/s 15
A - G
Possession Taken U/s19 Extent & No. of Sy.No. & Date Compensation Paid Court deposit process General Award Sy. No. Total Balance to be paid Remarks Prince Negotiation Meeting conducted dates
Extent
A -G
Sy.No. Sy.No. Sy.No. Sy.No. Sy.No.
1 WAP 1 (NH209) Malavalli - Maddur 63-A 115 8-28 8-28
(115)
Completed
07-02-2013
1-13 1/4 15 - - 15 100 Payment under progress 27.06.2014 &,
28.06.2014
2 Maddur - Huliyurdurga 63-B 411 15-07 1/2 14-01
(411)
Completed
03-11-2013
0-26 1/2 25 - - 25 386 Payment under progress 18.05.2013,
20.06.2014,
23.06.2014&
25.06.2014
13.08.2014
14.08.2014
3 Huliyurdurga - Kunigal 63-C 202 13-33 1/4 13-33
(202)
Completed
09-11-2012/td>
3-12 1/4 37 - - 37 165 Payment under progress 18.02.2013
4 Huliyurdurga bypass 63-BC 73 23-33 23-22 3/4
(73)
Completed
24-09-2013
- - - - - 73 Price Negotiation Meeting date awaited from AC (SDM) Price negotiation meeting to be conducted.
5 Kunigal - Tumkur (NH206) 63-D 185 13-22 1/2 13-14
(185)
Completed
20-09-2012
08.01.2014
3-05 3/4 73 - - 73 112 Payment under progress 15-03-2013,
18-05-2013
6 Tumkur - Koratagere 63-E 60 8-35 3/4 8-23 1/4
(60)
Completed
09-11-2012
7-31 12 - 41 53 7 U/s. 19 Additional Notification and submitted to Government 01.07.2014 14-06-2013
7 Koratagere - Madhugiri 63-F 72 4-18 3/4 4-17 1/2
(72)
Completed
03-11-2012
3-17 3/4 14 - 48 62 10 Payment under progress 14-06-2013
13-06-2013
10-06-2014
8 Madhugiri Bypass 63-FG 172 54-18 1/4 54-18 1/4
(-172)
Completed
28-12-2012
5-05 3/4 14 - - - 172 Payment under progress 27.05.2014 & 28.05.2014
(U/s 15 Notification addl. Sent to Govt on 08.10.2013)
Total 1336 148-05 3/4 145-29 1/4
(1336)
25-20 1/2 183 - 128 311 1025
1 WAP 2 Mudhol - Mahalingapura 63-FG 172 54-18 1/4 54-18 1/4
(-172)
Completed
28-12-2012
5-05 3/4 14 - - - 172 Payment under progress 27.05.2014 & 28.05.2014
(U/s 15 Notification addl. Sent to Govt on 08.10.2013)
2 Mahalingapura - Kabbur 19-B 352 44-01 1/4 43-33 3/4
(352)
Completed
31-08-2013
19.06.2014
6-10 1/4 75 - - - 277 08.01.2014
27.01.2014
24.01.2014
3 Kabbur - Chikkodi 19-C 39 4-22 4-17
(39)
Completed
01-02-2013
4-12 1/2 6 - 32 38 1 21.01.2014
4 Chikkodi - Nippani (NH4) 19-D 155 22-37 1/2 21-33 1/2
(155)
Completed
01-02-2013
20-21 1/2 20 - 135 155 0 21.01.2014
22.01.2014
Total 663 88-09 1/2 75-39 3/4
(663)
36-24 1/4 140 - 239 379 284
Grand Total 1999 236-15 1/4 222-07 1/24
(1999)
62-04 3/4 323 - 367 1309



List of World Bank Consultancies working for KSHIP-II

Sl No Supervision Consultant Description Contract Value (in INR) Start Date End Date Status
1 M/s EGIS International Ltd. In JV with EGIS-India and Aarvee Associates Construction Supervision Consultants for the Supervision of Construction and Contract Administration of the 5 EPC Contracts Rs 35,15,00,274 26-04-2011 30-09-2016 Completed
2 M/s ROUGHTON INTERNATION LTD. United Kingdom
is associated with M/s SATRA INFRASTRUCTURE MANAGEMENT SERVICES
Construction Supervision Consultants for the Supervision of Construction and Contract Administration of the 3 Annuity Coverted EPC Contracts (WAEP-3A, WAEP-3B & WAEP-4) Rs 19,55,37,136 06-07-2015 31-01-2021 In progress
3 URS Scott Wilson Bangalore Consultancy Services for Preparing of Detailed Project Reports for all WB & ADB packages Rs 80,00,000 01-01-2016 31-12-2016 Completed
Consultancy Services for Preparing of Detailed Project Reports for all WB & ADB packages Rs 80,00,000 01-01-2017 31-12-2017 In progress
4 M/s LEA Associates South Asia Independent Engineer (IE-1) for the Monitoring of WAP-1 Annuity Contract Package Rs 21,10,45,689 12-12-2014 31-01-2021 Annuity in progress
5 M/s Aarvee Associates Architect engineers & consultants Independent Engineer (IE-2) for the Monitoring of WAP-2 Annuity Contract Package Rs 13,71,99,100 19-01-2015 31-01-2021 Annuity in progress
6 M/s Allied Boston Consultancy India Pvt Ltd, New Delhi. QM/ISO certification- Documentation/manual preparation services (II Phase) Rs 1,69,40,000 17-11-2014 30-6-2020 In progress
7 M/s Allied Boston Consultancy India Pvt Ltd, New Delhi. Consultancy services for operationalisation of Environment Management System(EMS) ISO 14001 in KPWD Rs 71,01,000 26-11-2012 30-09-2017 Completed
8 M/s Indian Register Quality Systems, Bangalore Third Party Audit service for accreditation of ISO 14001-2004 to 14 KPWD offices Rs 18,11,956 16-3-2015 16-3-2018 In progress
9 M/s Allied Boston Consultancy India Pvt Ltd, New Delhi. Consultancy services for operationalisation of Environment Management System(EMS) ISO 14001 in KPWD Rs 26,45,000 26-12-2017 26-05-2018 Completed
10 M/s Intercert Pvt Ltd Third Party Audit services for award of ISO:14001:2015 certificate to 14 KPWD offices under KSHIP-II Rs 16,99,067 17-01-2019 17-07-2021 In Progress
11 M/s Vindhya e-Infomedia Pvt Ltd,Bangalore Establishment of Public Response Centre for PIU ,KSHIP Rs 49,43,959 13-10-2014 30-11-2016 Completed
Establishment of Public Response Centre for PIU ,KSHIP Suplimentary Agreement - 1 Rs 49,43,960 30-11-2016 30-06-2018 Completed
12 M/S Vicroads ,Australia Consultancy services to build Road Safety lead agency capacity in Transport Dept. Rs 7,65,00,000 10-1-2013 04-10-2015 Completed
13 M/s BIRDS NGO Services for Implementation of Resettlement Action Plan for North Karnataka Packages Rs 52,08,300 09-11-2009 31-12-2014 Completed
14 M/s Samaj Vikas M & E Consultants for Implementation of Resettlement Action Plan for both Packages Rs 38,48,136 09-11-2009 31-3-2015 Completed
15 M/s Centaur Informations Systems Pvt Ltd DBMS Consultant for LAQ & R&R Packages for KSHIP II Rs 11,82,800 12-07-2009 05-01-2014 Completed
16 M/s Simpro Business Solutions Pvt Ltd DBMS Consultant for LAQ & R&R Packages for KSHIP II Rs 7,21,200 07-01-2015 31-12-2015 Completed
17 M/s Mittal & Co., Chartered Accounts, Faridabad, Haryana Consultancy Services for Internal Audit of KSHIP-II Rs 8,00,000 15-11-2012 15-11-2013 Completed
18 M/s Patro & Co Consultancy Services for Internal Audit of KSHIP-II Rs 10,00,000 11-01-2014 31-12-2019 Completed
19 M/s Wipro Pvt Ltd,Bangalore IT/ICT/MIS enhancement services and action plan preparation and implementation Rs 67,25,559 05-01-2015 05-07-2016 Closed
20 M/s Saxena Consultancy services for HRD training enhancements and program delivery in PWD Rs 27,00,000 27-3-2013 25-5-2014 Completed
21 M/s Backend Bangalore Pvt Ltd,Bangalore Consultancy services for PWD implementation of project management framework and processes Rs 1,36,98,750 21-10-2012 21-10-2015 Completed
Rs 60,24,266 21-10-2015 30-6-2018 Completed
Rs 27,08,100 01-01-2020 31-12-2021 In Progress
22 M/s Gaurish Technologies Pvt Ltd,Bangalore Designing the Server/ Cloud server of required attributes and identifying / trialling software and modalities for hosting content. Rs 9,00,000 30-04-2014 31-01-2017 In progress
23 M/s MRCC Procurement of Server/ Cloud server with required performance, control, the flexibility to scale to in future. Rs 23,55,000 19-06-2015 19-06-2018 In progress
24 M/s MDRA Periodic Road User Satisfaction Survey-I Rs 42,88,107 02-07-2013 04-02-2014 Completed
25 M/s MDRA Periodic Road User Satisfaction Survey-II Rs 42,92,601 14-01-2015 30-06-2016 Completed
26 M/s MDRA Periodic Road User Satisfaction Survey-III Rs 45,20,580 30-07-2018 31-12-2018 Terminated
27 Mr. Shiva Kumar Menasinakai Mass Communication Expert Rs 11,40,000 02-07-2015 06-01-2016 Completed
28 Mr. T.S Ranganna Mass Communication Expert Rs 11,40,000 02-11-2016 01-11-2018 Closed
29 M/s Deccan consultants of Engineering Pvt,ltd,Delhi Independent Environmental monitoring (Pollution Control) for EPC roads & Annuity roads Rs 76,87,829 25-11-2011 30-06-2020 Completed
30 M/s HIMS Ltd, New Zeland Consultancy services for Collection of Non-CRN Road condition data for Population and operationalisation of Road information system and pavement management system. Rs 19,37,86,692 25-11-2014 25-11-2017 Completed
31 M/s Urs Scot Wilson Bangalore Safe Corridor Program-Entrusting preparation of DPR of SCDP Rs 45,00,000 17-10-2014 17-07-2015 Completed
32 M/s Pricewaterhouse coopers Ltd., New Delhi Transaction Advisory services for procurement of 4 Annuity Contract Packages Rs 45,30,000 16-09-2011 16-09-2015 Completed

 

List of Asian Development Bank Consultancies working for KSHIP-II

Sl No Supervision Consultant Description Contract Value (in INR) Start Date End Date Status
1 M/s SMEC Internationals Pvt Ltd Construction Supervision Consultants for the supervision construction and Contract Administration of ADB Packages Rs 42,10,49,366 12-06-2012 31-12-2019 Completed
2 M/s.EGIS International S.A.in JV with M/s. EGIS India Consulting Engineers Pvt.Ltd Consultancy Services to Support the Establishment and operation of the Planning and Road Asset Management Centre(PRAMC) for PWD Rs 28,42,60,773 12-02-2013 28-02-2019 Completed
3 M/s SSRDO NGO services for implementation of Resettlement Acion Plan for North Karnataka Packages Rs 41,13,375 09-05-2011 31-03-2015 Completed
4 M/s SCODWES NGO services for implementation of Resettlement Acion Plan for South Karnataka Packages Rs 51,19,905 09-05-2011 31-03-2015 Completed
5 M/s CMSR M&E Consultants for implementation of Resettlement Action Plan for both packages Rs 39,03,750 11-05-2011 31-05-2015 Completed
6 M/s Sneha Test House Consultancy services for Environmental Monitoring (Pollution) for ADB assisted project roads under KSHIP-II Rs 58,81,200 30-11-2012 30-06-2020 Completed
7 M/s Pricewaterhouse Coopers Ltd., New Delhi Hiring of consulting services for evaluating post impact of GST implementation onworks contract EPC packages which were started before GST period Rs 15,00,000 26-06-2019 - In Progress
WAEP4 AEP3A AEP3B AEP9C AEP9B AEP9A AEP6B AEP6A WAEP3B WAEP3A Note: Mouse over on the map to zoom



WAP-1 : Malavalli to Pavagada
Road Length: 194.34 Km ; Duration: 30 Months Construction + 90 Months Maintenance
Construction Cost: Rs 576 Crores ; Annuity Cost(Biannual): Rs 1306 Cr(239 Cr + 15 Installments of Rs 71.15 Cr)
Construction Schedule: 06-Nov-2014 to 06-May-2017
Executing Agency: M/S Mysore Bellary Pvt Ltd(M/S Sadbhav-GKC(JV))
Construction Supervision Consultant: M/S LEA Associates South Asia Private Ltd
WAP-2 : Mudhol to Nippani
Road Length: 107.94 Km ;   Duration: 24 Months Construction + 96 Months Maintenance
Construction Cost: Rs 331 Crores ; Annuity Cost(Biannual): Rs 768 Cr(136 Cr + 16 Installments of Rs 39.49 Cr)
Construction Schedule: 19-Jan-2015 to 19-Jan-2017
Executing Agency: M/S Ashok Buildcon-GVR(JV)
Construction Supervision Consultant: M/S Aarvee Associates Architects Engineers& Consultants Pvt Ltd
WAEP-3A : Shimoga-Shikaripura-Anandapuram
Road Length: 82 Km ;   Duration: 32 Months
Construction Cost: Rs 264.73 Crores ; Construction Schedule: 28-4-2015 to 27-12-2017
Executing Agency: M/S Patel Engineering Pvt Ltd
Construction Supervision Consultant: M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd
WAEP-3B : Shikaripura-Anavatti-Hangal
Road Length: 71.63 Km ;   Duration: 29 Months Construction
Construction Cost: Rs 224.7 Crores ; Construction Schedule:
Executing Agency: M/S RNS Infrastructure Ltd
Construction Supervision Consultant: M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd
WAEP-4 : Managuli-Devapura
Road Length: 109.953 Km ;   Duration: 33 Months Construction
Construction Cost: Rs 317.05 Crores ; Construction Schedule:
Executing Agency: M/S Sadbhav Engineering Ltd
Construction Supervision Consultant: M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd.
WEP1 : Hoskote to Chintamani Bypass of SH-82
Road Length: 52.4 Km ;   Duration: 30 Months
Contract Amount: Rs 98.22 Crores
Schedule: 13-Aug-2011 to 12-Feb-2014
Executing Agency: M/s Lanco Infratech Ltd
Construction Supervision Consultant: EGIS International
WEP2a : Haveri to Hanagal SH-2
Road Length: 31.784 Km ;   Duration: 21 Months
Contract Amount: Rs 92.54 Crores
Schedule: 02-Mar-2013 to 22-Dec-2014
Executing Agency: M/s DRN Infrastructure, Hubli
Construction Supervision Consultant: EGIS International
WEP2b : Hanagal to Tadasa of SH-1, SH-2
Road Length: 43.476 Km ;   Duration: 21 Months
Contract Amount: Rs 97.87 Crores
Schedule:
Executing Agency: M/S DRN Infrastructure
Construction Supervision Consultant: EGIS International
WEP3 : Dharwad to Saundatti of SH-34
Road Length: 36 Km ;   Duration: 41 Months
Contract Amount: Rs 84.44 Crores
Schedule: 28-Jul-2011 to 01-Dec-2014
Executing Agency: M/s RVCPL-RIDL JV
Construction Supervision Consultant: EGIS International
WEP4 : Tinthni to Kalmala of SH-61 & SH-15
Road Length: 73.80 Km ;   Duration: 36 Months
Contract Amount: Rs 160.79 Crores
Schedule: 13-Aug-2011 to 12-Aug-2014
Executing Agency: M/s Patel Engineering Ltd
Construction Supervision Consultant: EGIS International
WEP5 : Chowdapur to Gulbarga of SH-22
Road Length: 28.63 Km ;   Duration: 21 Months
Contract Amount: Rs 61.55 Crores
Schedule: 19-Jul-2011 to 18-Apr-2013
Executing Agency: M/s SRK-KCL JV
Construction Supervision Consultant: EGIS International
AEP1 : Magadi to NH-48 to Koratagere in Tumkur and Ramanagara Districts
Road Length: 68.20 Km ;   Duration: 33 Months
Contract Amount: Rs 116.69 Crores
Schedule: 21-Mar-2012 to 20-Dec-2014
Executing Agency: M/s. KNR Constructions Ltd
Construction Supervision Consultant: SMEC International
AEP2 : Pavagada to AP Border of SH-3
Road Length: 23.205 Km ;   Duration: 18 Months
Contract Amount: Rs 43.30 Crores
Schedule: 29-Mar-2012 to 28-Sep-2013
Executing Agency: M/s. GVR-RMN (JV)
Construction Supervision Consultant: SMEC International
AEP3 : Gubbi to Mandya of SH-84
Road Length: 108.62 Km ;   Duration: 33 Months
Contract Amount: Rs 196.81 Crores
Schedule: 21-Mar-2012 to 06-Dec-2014
Executing Agency: M/s. KMC-VDB (JV)
Construction Supervision Consultant: SMEC International
AEP3A : Gubbi-Beeragonahalli (near Yediyur) of SH-84
Road Length: 49.03 Km ;   Duration: 21 Months
Contract Amount: Rs 122.38 Crores
Schedule:
Executing Agency: M/S DRN Infrastructure, Hubli-30
Construction Supervision Consultant: SMEC International
AEP3B : Beeragonahalli (near Yediyur) - Mandya of SH-84
Road Length: 59.09 Km ;   Duration: 33 Months
Contract Amount: Rs 198.27 Crores
Schedule:
Executing Agency: M/S D.P Jain & Co Infrastructure Pvt Ltd
Construction Supervision Consultant: SMEC International
AEP4 : Jaglur to NH-13 and from SH-19 of KSHIP Road to Molakalmuru of SH-2
Road Length: 14.38 Km ;   Duration: 15 Months
Contract Amount: Rs 31.26 Crores
Schedule: 21-Mar-2012 to 21-Jun-2013
Executing Agency: M/s. GVR-RMN (JV)
Construction Supervision Consultant: SMEC International
AEP5 : Padubidri to Karkala of SH-1
Road Length: 27.80 Km ;   Duration: 18 Months
Contract Amount: Rs 61.27 Crores
Schedule: 05-Mar-2012 to 20-Sep-2013
Executing Agency: M/s. RNS Infrastructure Ltd
Construction Supervision Consultant: SMEC International
AEP6 : Davangere to Birur of SH-76
Road Length: 105.63 Km ;   Duration: 33 Months
Contract Amount: Rs 202.57 Crores
Schedule: 21-Mar-2012 to 20-Dec-2014
Executing Agency: M/s.Gammon India Ltd
Construction Supervision Consultant: SMEC International
AEP6A : Davangere to Channagiri of SH-76
Road Length: 53.65 Km ;   Duration: 21 Months
Contract Amount: Rs 181.45 Crores
Schedule: 15-Dec-2015 to 15-Sep-2017
Executing Agency: M/S JMC Projects (India) Ltd.
Construction Supervision Consultant: SMEC International
AEP6B : Chennagiri to Birur of SH-76
Road Length: 51.98 Km ;   Duration: 22 Months
Contract Amount: Rs 136.78 Crores
Schedule: 1-Sep-2015 to 1-Jul-2017
Executing Agency: M/s D P Jain & Co, Infrastructure Pvt. Ltd.,
Construction Supervision Consultant: SMEC International
AEP7 : Shelvadi to Mundargi of SH-45
Road Length: 63.44 Km ;   Duration: 33 Months
Contract Amount: Rs 121.25 Crores
Schedule: 21-Mar-2012 to 20-Dec-2014
Executing Agency: M/s. KNR Constructions Limited
Construction Supervision Consultant: SMEC International
AEP8 : Mudgal to Gangawathi of SH-29
Road Length: 74.20 Km ;   Duration: 36 Months
Contract Amount: Rs 152.63 Crores
Schedule: 26-Mar-2012 to 25-Mar-2015
Executing Agency: M/s. KNR Constructions Ltd
Construction Supervision Consultant: SMEC International
AEP9 : Soundatti to Kamatagi(including Mulur Ghat) of SH-34 and SH-14
Road Length: 130.13 Km ;   Duration: 36 Months
Contract Amount: Rs 225.50 Crores
Schedule: 21-Mar-2012 to 20-Mar-2015
Executing Agency: M/s. Ramky Infrastructures Ltd
Construction Supervision Consultant: SMEC International
AEP9A : Saundatti to Halagatti Junction(Ramdurga) (including Mullur ghat)
Road Length: 42.065 Km ;   Duration: 21 Months
Contract Amount: Rs 138.24 Crores
Schedule:
Executing Agency: M/S DP Jain & Co Infrastructure Pvt Ltd
Construction Supervision Consultant: SMEC International
AEP9B : Halagatti Junction(Ramdurga) to Badami(including Badami Bypass)
Road Length: 45 Km ;   Duration: 21 Months
Contract Amount: Rs 146.04 Crores
Schedule:
Executing Agency: M/S RNS Infrastructure Ltd
Construction Supervision Consultant: SMEC International
AEP9C : Badami Bypass junction - Pattadakallu - Kamatagi
Road Length: 43.13 Km ;   Duration: 21 Months
Contract Amount: Rs 110.89 Crores
Schedule:
Executing Agency: M/S Ashoka Buildcon Ltd
Construction Supervision Consultant: SMEC International