SE1 ( Southern Region ) WEEKLY WORK DONE AMOUNT REPORT from 15-Feb-21 to 22-Feb-21
Sl.No. Work Description of Road Contractor Length(Km) Total Project Cost(INR Crores) Upto Previous Month,Cr Upto Previous Week,Cr Target,Cr Achieved,Cr Slippage,Cr
This Week Upto Date This Week Upto Date This Week Upto Date
WB
1 WAP1 Malavalli to Pavagada Sadbhav 193.34 1371 0 0 0 684 0 0 0 -684
2 WAEP3A Shimoga - Shikaripura - Anandapura Patel 82.04 264.733 269.51 269.51 0 285.74 0 269.51 0 -16.23
Total: 275.38 1,635.73 269.51 269.51 0.00 969.74 0.00 269.51 0.00 -700.23
ADB
1 AEP-3A Gubbi - Beeragonahalli DRN 49.03 122.39 167.88 167.88 0 154.26 0 167.88 0 13.62
2 AEP-3B Beeragonahalli - Mandya DP Jain 59.59 198.27 238.68 238.68 0 236.02 0 238.68 0 2.66
3 AEP-6A Davanagere - Channagiri JMC 52.27 181.45 166.58 166.58 0 172.61 0 166.58 0 -6.03
4 AEP-6B Chennagiri - Birur DP Jain 50.58 136.78 138.73 138.73 0 151.98 0 138.73 0 -13.25
5 ROB-1 Ch@7+695 on Davanagere - Channagiri road KNR 1.38 41 44.97 44.97 0 47.71 0 44.97 0 -2.75
6 ROB-2 Ch@44+855 on Channagiri - Birur road Venkata 1.4 40.101 27.31 27.31 0 38.61 0 27.31 0 -11.3
Total: 214.25 719.99 784.14 784.14 0.00 801.19 0.00 784.14 0.00 -17.05