WAEP3A ನ ಪರಿಸರ ನಿರ್ವಹಣೆ





Bill of Quantities
Sl No Description Unit Work Done Quantity Amount in Rs
BILL NO: 10 - Safety in Road Construction Zone
10.01 Supplying and fixing sign boards including the cost of posts, fixgtures, foundation, fitting and fixing, Sheeting wil be made of encapsulated lens type of Retro-reflective type and messages/borders will be screen printed complete sa per Technical Specification Clauses 112 & 801 and as directed by Engineer Technical Specification Cl. 112 & IRC SP 55-2001      
i) Octagonal 900 x 900 mm type IX No - -
ii) Circular 600 dia type IX No - -
iii) Informatory as per drawing type IX Sqm (-13.515) 1,66,265
iv) Cautionary warning signs (Triangular 900 sides) type IX No - -
10.02 Providing of red fluorescent with white reflective sleeve traffic cone made of low density polyetylene (LDPE) material with a swuare base of 390x390x35 mm and a height of 770mm, 4 Kg in weight, placed at 1.5m interval, all as per BS 873 inc luding cost of all materials, labour, loading, unloading, lead, lift, transporting etc complete Technical Specification Cl. 112 & IRC SP 55-2001 No - -
10.03 Installation of a steel portable barricade with horizontal rail 300mm wide, 2.5m in length fitted on a frame made with 45x45x5 mm angle iron section, 1.5m in height horizontal rail painted (2coat) with yellow and white strips, 150mm in width at angle of 45 degree, Aframe painted with 2 coats of yellow paint, complete as perIRC:SP:55-2001 ncluding cost of all materials, labour, loading, unloading, lead,lift, transporting etc omplete sa per Technical Specification Cl.112 No 30 1,36,800
10.04 Provision of metal drum/empty bitumen drum delineator, 300mm in diameter,800mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100mm wide 2 coats fitted with reflectors 3 Nos of 7.5cm dia,all as per IRC:SP:55-2001 including cost of all materials, labour, loading, unloading lead lift, transporting etc., complete as per Technical Specification Cl.112 No 4 2,220
10.05 Providing plastic crash barrier as per drawing and per the of the Engineer(1000X490X780MM size)(LWH) as per Technical Specification Cl.112 No 6 33,300
10.06 Providing Barricading/Caution Tapes of High quality PVC tape tube type to Enclose construction area as per Technical Specification Cl.112 Lm - -
BILL NO: 11 - Implementation of Environmental Management Action Plan to be executed under Civil Works Contract
11.01 A. Carting away the unserviceable materials from work site to the nearest disposal site (up to a lead of 10Km) and disposing the same in disposal pits or borrow areas including depositing unserviceable materials in layers and manual compaction as per Technical Specification Clause. 111 Cum - -
  B. The 30 cm top layer of disposal pit shall be provided with good earth, suitable for development of vegetation/plantation. All work shall be carried out as per specification and approval of the Engineer in Charge as per Technical Specification Clause.111 Sqm - -
11.02 Turfing at ground level at disposal pits for un-serviceable material as per specifications and approval of the Engineer in Charge as per Technical Specification Clause.111 Sqm - -
11.03 Regular water sprinkling (at least 4 times) per day atall construction sites for suppression of visible dust levels. as per Technical Specification Clause.111 KM - -
11.04 Construction of recharge pits within the selected water bodies along the projectroad as per approved design and Drawing as developed by central ground water board asper tech. Spec clause 111 and as per Drawing No U/T/17 No - -
11.05 Construction of silt traps at the discharge points of channels into to fresh water bodies across the project road as per the Standard Details provided in the as per Technical Specification Clause. 111 and as per Drawsing no. U/T/16 Lm - -
11.06 Providing informatory sign boards (Informatory/caution messages)for road users forproviding information about ecologically sensitive areas, wild life crossing points(if any), important tourist locations, etc as applicable.The specification of sign boards shall conform to relevant IRC specifications. The locations for Informatory sign boards are given in as per Technical Specification Clause. 111 Sqm - -
11.07 Utilisation of unserviceable material obtained from Road way excavation for widening and construction of Cross roads. No - -
11.08 Construction of 30cm thick clay lined (at bottom and sides) pits for safe disposal of scarified bitumen including carriage (up to a lead of 10km), depositing bitumen in layers of 15 cms with manual compaction and covering the pit with 20cm thick good earth as top layer at ground level all complete as per Typical Drawing as given in the as per technical specification Clause 111 Sqm - -
11.09 Turfing at ground level at disposal pits for scarified bitumen as per specifications and approval of the Engineer in Charge. Sqm - -
11.10 Periodic air quality monitoring during construction stage at construction camp sites, bitumen hot mix plants, crusher plants (if specifically established for Project), at major settlement areas along project road. The parameters to be monitored are SPM, RPM, SO2, NOx and CO, Lead. Each monitoring schedule shall be over a duration of 24 hours (in 8 hour shifts), once in a quarter and for 2 Years). The tests are to conducted in accordance CPCB norms and as per technical specification Clause 111 Nos. - -
11.11 Water quality monitoring during construction phase at locations given in Appendix . The sampling shall be carried out once in a quarter for 2 years and cover all parameters as per IS10500 including heavy metals as per technical specification Clause 111 Nos. - -
11.12 Noise quality monitoring at specified silent receptors along Project Road, at construction camp sites, bitumen hot mix plants, crusher plants(if specifically established for Project), and at major settlement areas along project road. – Each monitoring schedule shall be over a duration of 12hours (6Am to 6PM), once in a quarter and for 2 Years). The monitoring shall be carried out in accordance with CPCB norms at locations given as per technical specification Clause 111 Nos. - -
11.13 Soil quality monitoring at construction camp sites, work shop areas, oil/lubricant handling areas, bitumen hot mix plants, at all parking lay byes, vehicle servicing stations along Project Road. Parameters shall include N, P, oil and grease, heavy metals, C/N ratio, pH, organic matter and carried out once in a quarter at all locations for 2 years as per details given as per technical specification Clause 111 Nos. - -
11.14 Providing Oil Interceptors at the fuel/oil storage camps or Construction camps as per technical specification Clause 111 and Drawing no.WAEP-4/U/T/19 Nos. - -
11.15 Providing Personal Protective Equipment to labours during construction Phase of the projects per technical specification Clause 111 Cost/Person/annum - -
11.16 Provision for two health check ups for the carcinogens from bituminous fumes, which may inhaled during road paving works. The first health check up prior to induction of the personnel into the construction works and the last health check up prior to the discharge of the personnel from the construction works as per technical specification Clause 111111 Cost/Person/annum - -
11.17 Item No. 11.17 Not Used - - -
11.18 Providing,Commissioning,operation & Maintenance of Mobile Toilet Van(MTV) including cost of Fabrication of 3 seat mobile bio-toilets mounted on tractor trailer of size 3.70Mtr x 3.00Mtr x 3.50M (LxBxH) from ground level. MTV having two sections consist of 3 WCs and 1 washing cabin (1 Ladies+ 2 Gents) of size 0.90M x 0.90M complete with Chassis, Suspension consisting of two axles 75mm x 75mm with taper roller bearings , Hub, Road Springs 4 nos , Tyre-Tubes of requisite size 16 ply etc. Cabin Structures and Panels, Doors, Roof Structure, Path Ways, Stairs, Floor Panel Integrated Squatting Pan, Wash Basins, Mirrors, Clean Water Tank, Electric Points, Solar Panel with Battery and LED Lights, Towing Arrangement, Tool Box, FRP Molded/MS Bio-Digester Tank of suitable size with capacity of (1200 Liters ) and other accessories as required for complete one job. Ls 0.036 54,600
ಕೊನೆಯದಾಗಿ ನವೀಕರಿಸಲಾಗಿದೆ: 02-Sep-2023 13:00