AEP3B ನ ಪುನರ್ವಸತಿ ಮತ್ತು ಪುನರ್ವ್ಯವಸ್ಥೆ



ಹಿಂದಕ್ಕೆ As on 31-May-2018

 

NON TITLE HOLDERS

Sl. No. Type of R&R Assistance Target Revised Progress Percentage Remarks
1 ID Cards Issued 349 168 167 99  
2 Allotment of House Plots 02 02 02 100  
3 Construction grant paid for houses 04 02 - - Construction cost placed with EE to be released to DPs based construction progress
4 Subsistence allowance paid 96 54 52 98  
5 Shifting allowance paid 96 54 52 98  
6 IGA Support provided 92 52 41 79 11 DPs have not shifted, hence IGA not released.
7 Replacement cost paid for Encroachers 195 114 102 89  
8 Tenant - - - -  
9 Shifting of CPRs 166 166 166 100  
10 No. of PAPs received all benefits 349 168 143 85