AEP1 ನ ಪುನರ್ವಸತಿ ಮತ್ತು ಪುನರ್ವ್ಯವಸ್ಥೆ



ಹಿಂದಕ್ಕೆ As on 31-May-2018



NON TITLE HOLDERS

Sl. No. Type of R&R Assistance Target Revised Progress Percentage Remarks
1 ID Cards Issued 63 81 81 100 -
2 Allotment of House Plots 01 01 01 - DP was released Shifting & Subsistence allowance; But, before release of construction cost he expired, hence progress is taken as 100%.
3 Construction grant paid for houses 01 01 - - -
4 Subsistence allowance paid 32 35 35 100  
5 Shifting allowance paid 32 35 35 100  
6 IGA Support provided 31 34 34 100  
7 Replacement cost paid for Encroachers 31 46 46 100 -
8 Tenant - - - -  
9 Shifting of CPRs 301 301 301 100  
10 No. of PAPs received all benefits 63 81 81 100