WEP3 ನ ಪರಿಸರ ನಿರ್ವಹಣೆ


Back As on 31-July-2015
Bill of Quantities
Sl No Description Unit Planned BoQ Quantity Approved Quantity
BILL NO. 10-SAFETY IN ROAD CONSTRUCTION ZONE
10.01 Supplying and fixing sign boards including the cost of posts, fixtures, foundation, fitting and fixing. Sheeting will be made of encapsulated lens type of Retro-reflective type and messages/ borders will be screen printed complete as per Technical Specification clause 801 and as directed by Engineer.      
  Octagonal 900x 900 mm No. 20 11
  Circular 600 dia No. 15 8
  Informatory as per drawing  Sq.m 30 16
  Cautionary warning signs (Triangular 900 sides) TypeIII No. 15 8
10.02 Providing of red fluorescent with white reflective sleeve traffic cone made of low density polyethylene(LDPE) material with a square base of 390x390x35mm and a height of 770mm, 4Kg in weight, placed at 1.5m interval, all as per BS 873 including cost of all materials, labour, loading, unloading, lead, lift, transporting etc complete Technical Specification section & IRC SP 55-2001. No. 150 55
10.03 Installation of a steel portable barricade with horizontal rail 300mm wide, 2.5m in length fitted on a frame made with 45X45X5 mm angle iron section, 1.5m in height, horizontal rail painted(2coat) with yellow and white strips, 150mm in width at angle of 45degree, A frame painted with 2 coats of yellow paint, complete as per IRC:SP:55-2001 including cost of all materials, labour, loading, unloading, lead, lift, transporting etc complete. No. 50 -
10.04 Provision of metal drum/empty bitumen drum delineator, 300mm in diameter, 800mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100mm wide 2 coats fitted with reflectors 3 Nos of 7.5cm dia, all as per IRC:SP:55-2001 including cost of all materials, labour, loading, unloading, lead lift, transporting etc., complete. No. 150 -
10.05 Providing plastic crash barrier as per drawing and per the directions of the Engineer(1000X490X780MM size)(LWH). No. 75 29
10.06 Providing Barricading/Caution Tapes of High quality PVC tape tube type to Enclose construction area as per Technical Specification. Lm 2,500 1,300
BILL NO. 11-IMPLEMENTATION OF ENVIRONMENTAL MAANAGEMENT ACTION PLAN TO BE EXECUTED UNDER CIVIL WORKS CONTRACT
11.01 A. Carting away the unserviceable materials from work site to the nearest disposal site (up to a lead of 5km) and disposing the same in disposal pits or borrow areas including depositing unserviceable materials in layers and manual compaction. Appendix:1 Cum 33,309 29,616.3
  B.The 30 cm top layer of disposal pit shall be provided with good earth, suitable for development of vegetation/plantation. All work shall be carried out as per specifications and approval of the Engineer in Charge. Sq.m. 100,000 70,000
11.02 Turfing at ground level at disposal pits for un-serviceable material as per specifications and approval of the Engineer in Charge. Sq.m 100,000 -
11.03 Regular water sprinkling (at least 4 times) per day at all construction sites for suppression of visible dust levels.
Note: This item is to be operated after the completion of earthwork to suppress the visible dust levels. Cost of watering during compaction of earthwork is deemed to be already covered under civil works.
Km 39 20
11.04 Construction of Recharge pits within the selected water bodies along the project road as per approved design and drawing as developed by Central Ground Water Board (Ref Appendix-2 for details). Nos. 6 -
11.05 Construction of silt traps at the discharge points of channels into to fresh water bodies across the project road as per the Standard Details provided in the Appendix-3. M 6 -
11.06 Providing informatory sign boards (informatory /caution messages) for road users for providing information about ecologically sensitive areas, wild life crossing points (if any), important tourist locations, etc as applicable. The specifications of sign boards shall conform to relevant IRC specifications. The locations for informatory sign boards are given in Appendix-4. Sq.m 2 -
11.07 Construction of 30cm thick clay lined (at bottom and sides) pits for safe disposal of scarified bitumen including carriage (up to a lead of 10km), depositing bitumen in layers of 15 cms with manual compaction and covering the pit with 20cm thick good earth as top layer at ground level all complete as per Typical Drawing as given in the Appenxix:5 Nos. 24 22
11.08 Turfing at ground level at disposal pits for scarified bitumen as per specifications and approval of the Engineer in Charge. Sq.m 8,138 -
11.11 Periodic air quality monitoring during construction stage at construction camp sites, bitumen hot mix plants, crusher plants (if specifically established for Project), at major settlement areas along project road. The parameters to be monitored are SPM, RPM, SO2, NOx and CO, Lead. Each monitoring schedule shall be over a duration of 24 hours (in 8 hour shifts), once in a quarter and for 2 Years). The tests are to conducted in accordance CPCB norms at locations given in Appendix : 7) Nos. 42 24
11.12 Utilisation of unserviceable material obtained from Road way excavation for widening and construction of Cross roads. Cum 6,720 -
11.13 Water quality monitoring during construction phase at locations given in Appendix . The sampling shall be carried out once in a quarter for 2 years and cover all parameters as per IS10500 including heavy metals as per details given in Appendix:7 Nos. 18 9
11.14 Noise quality monitoring at specified silent receptors along Project Road, at construction camp sites, bitumen hot mix plants, crusher plants(if specifically established for Project), and at major settlement areas along project road. – Each monitoring schedule shall be over a duration of 12hours (6Am to 6PM), once in a quarter and for 2 Years). The monitoring shall be carried out in accordance with CPCB norms at locations given in Appendix:7 Nos. 42 24
11.15 Soil quality monitoring at construction camp sites, work shop areas, oil/lubricant handling areas, bitumen hot mix plants, at all parking lay byes, vehicle servicing stations along Project Road. Parameters shall include N, P, oil and grease, heavy metals, C/N ratio, pH, organic matter and carried out once in a quarter at all locations for 2 years as per details given in Appendix:7 Nos. 32 10
11.16 Providing Oil Interceptors at the fuel/oil storage camps or Construction camps as per Typical Drawing in Appendix:8 Nos. 1 -
11.17 Providing Personal Protective Equipment to labours during construction Phase of the project (Appendix:9) cost/ person/ annum 100 -
11.18 Provision for two health check ups for the carcinogens from bituminous fumes, which may inhaled during road paving works. The first health check up prior to induction of the personnel into the construction works and the last health check up prior to the discharge of the personnel from the construction works. cost/ person 100 -