Rehabilitation & Resettlement for WAP1



Back As on 31-May-2018



NON TITLE HOLDERS

Sl. No. Type of R&R Assistance Target as per RIP Revised target Progress Percentage Remarks
1 ID Cards Issued 550 381 381 100  
2 Allotment of House Plots 08 13 13 100  
3 Construction grant paid for houses 08 13 12 93 One under construction.Part payment made.
4 Subsistence allowance paid 110 197 197 100 -
5 Shifting allowance paid 110 210 210 100 -
6 IGA Support provided 103 189 189 100 26 out of 34 tenents allowed IGA in Kunigal
7 Replacement cost paid for Encroachers 35 171 171 100  
8 Tenant 0 34 34 100 All are assisted fully.
9 Shifting of CPRs 736 776 776 100  
10 No. of PAPs received all benefits 550 381 380 99  

TITLE HOLDERS

Sl. No. Type of R&R Assistance Target as per RIP Revised Target Progress Percentage Remarks
  Assistance for loss of Residential structure          
1 Subsistence allowance paid 0 23 23 100  
2 Shifting allowance paid 0 23 23 100 The Revised target may vary after completion of Verification of the affected structures.
3 Allotment of House Plots / Possessing Homested land 0 23 23 100  
4 Construction grant paid for houses 0 23 23 100
5 Site Development cost 0 18 18 100
6 Resettlement allowance 0 18 18 100 Land value inrespect of Five PAPs deposited in Court, they were treated as NTHs.
  Assistance to Marginal Farmers          
1 Subsistance allowance 0 0 38 - Total applications received : 65 Assistance released so far:38 Endorsement issued:12 Under examination:15
2 IGA 0 0 38 -