Rehabilitation & Resettlement for WAEP4



Back As on 31-May-2018



NON TITLE HOLDERS

Sl. No. Type of R&R Assistance Target as per RIP Revised target Progress Percentage Remarks
1 ID Cards Issued 226 349 349 100  
2 Allotment of House Plots 30 34 34 100  
3 Construction grant paid for houses 30 34 34 100  
4 Subsistence allowance paid 178 254 228 90  
5 Shifting allowance paid 178 293 293 100  
6 IGA Support provided 148 259 159 100 Two PAPs not found after receiving Shifting & Subsistance allowance. Hence IGA not released. Hence progress may be taken as 100%
7 Replacement cost paid for Encroachers 48 56 56 100  
8 Tenant - - - - -
9 Shifting of CPRs 106 107 106 99  
10 No. of PAPs received all benefits 226 349 349 100